The objective of the project was to ensure compliance with the national and EU legislations within the transition periods agreed between Romania and the EU for the environmental sector, assistance to the project promoters in developing local capacity for future project development and the definition of a long term phased investment programme.

The project included the following activities:

  • Selective collection, collection, transfer and transport (14 transfer stations, 25 civic amenity sites) and storage of solid residues
  • Set-up and management of adequate waste treatment and disposal facilities (6 new ecological landfills, 1 compost facility, 5 sorting plants, etc.)
  • Improvement of the environmental situation by closure of inappropriate waste deposits (22 landfills and about 1,200 dumpsites)
  • Institutional strengthening by forming of Intercommunity Development Associations, adjustment of Romanian legislation and capacity building
ClientCentral Finance and Contracts Unit, Romania
Financing AgencyEuropean Commission, Belgium
LocationBotosani, Calarasi, Olt, Suceava, Vaslui, Romania
Services Period2007 – 2011
Project Cost146 million EUR
Technical Data
  • Total area
29,000 km²
  • Inhabitants
2.9 million
Services
  • Location and geological-geotechnical-hydro geological investigations of six landfill sites
  • Development of master plans, macro affordability assessments, institutional analysis and improvement
  • Procurement strategies, feasibility studies, financial and economic analysis and EIA for Botosani, Calarasi, Olt, Suceava and Vaslui counties
  • Preparation of five applications for EU co-financing and supporting documents, detailed design and tender documents (FIDIC)

NEWS

April 1st, 2024

January 29th, 2024

“La Atarjea” Wastewater Treatment Plant

GKW Consult GmbH (GKW) and its local consortium partner Agua Energía y Minería (AEM) (former…

November 20th, 2023

The Industrial Water Management department is currently working on two new projects for data center operators

For four years, the team has been working on projects for private clients in a future market that…