India, Kerala Water Supply Project

Water Intake Kozhikode

The project comprised the implementation of 5 independent water supply schemes  Thiruvanthapuram, Meenad, Cherthala, Kozhikode and Pattuvam, and the institutional strengthening and training of staff of the Kerala Water Authority.

The objectives of this extensive project are to provide new water supply systems and to rehabilitate existing water supply systems in two urban regions, Kozhikode and Thiruvanthapuram, and to construct completely new supply water supply systems for three rural regions, namely Pattuvam (Kannur District), Cherthala (Alappuzha District) and Meenad (Kollam District). The ultimate project design horizon is 2036.

In total the project will in its ultimate stage improve/provide access to potable water supply for 3.39 million existing and 0.7 million new consumers residing in the project areas. All of the new works include Intake Structures, Water Treatment Plants, Transmission Mains, Reservoirs, Distribution Net-works and associated chlorine contact tanks, booster pumping stations, rechlorination stations, treated water storage tanks, telemetry systems etc. 

Client

Kerala Water Authority, Kerala, India

Financing Agency

Japan International Cooperation Agency, Japan

Location

Kerala, India

Services Period

2003 - 2015

Project Cost

about 315 million EUR

Technical Data

  • Construction of 5 water treatment plants (total) 518,000 m³/d
  • Pumping station and booster pumping stations
  • Clear water reservoirs
  • Installation of new central telemetry systems
  • Construction of new transmission main systems
  • Construction of new distribution systems

Services

  • Review and finalization of the existing feasibility reports, detailed engineering designs, surveys, geotechnical investigations, tender preparation according to FIDIC red and yellow book, bid evaluation
  • Design elements: water abstraction works and intakes, water treatment plants, transmission mains with ancillary structures incl. automation, storage tanks and pumping stations incl. automation, and distribution system. 
  • Construction phase: project management assistance services, preconstruction services, supervision services during construction, services for institutional strengthening (KWA), training and general advisory services. Services for institutional strengthening (KWA), training and general advisory services. 

NEWS

August 2nd, 2024

Signing of the World Bank funded Design, Management & Supervision Consultancy (DMSC)

On the 31st July 2024 GKW signed the World Bank funded Design, Management & Supervision Consultancy…

July 2nd, 2024

Christoph Grass becomes managing director of GKW Consult in July

As of July 2024 Christoph Grass has taken over the position of the Managing Director at GKW Consult.

May 17th, 2024

GKW Consult at the IFAT Munich 2024

From May 13th to 17th, GKW Consult GmbH and GFA Consulting Group, both members of the GFA Group,…