The extra production capacity will provide relief from the general water shortage in the area. It is estimated, that this extra production capacity will cover the projected water demand of the coming 5 to 10 years. It will particularly improve the water supply to the low income housing areas.

Field of Activity: Water Supply
Uganda, Gaba III Water Treatment Plant
Services
- Review of contractors designs and preparation of environmental impact assessment report (pre-construction period)
- Supervision of Construction (Construction period) and
- Superintendence over the one year Defects Liability Period
Technical Data
- Clear Water Production 925 l/s
- Raw Water intake 1065 l/s
Project Facts
Location Gaba, Kampala, Uganda
Client National Water and Sewerage Corporation, Uganda
Financing Agency KfW, Germany
Service Period 2002 – 2013
Project Cost 145 million EUR